07 Construction log

April 2025

The construction of the entire building structure has been completed 100%. Window joinery installation is underway on the 14. 14th and 15th floors of stairwells A and B. Roof insulation works are in progress on stairwell A. Finishing works are ongoing in the building’s main entrance lobby. Land development (PZT) is being carried out in the patio area near stairwell B. Installation of the aluminum façade has begun on the 16th floor of stairwell B. Elevator installation is in progress in stairwell A. Glass balustrades are being mounted 13. on the 13th and 14th floors of building A, and on the 13th, 14th, and 15th floors of building B. Finishing elements are currently being installed in stairwells C and D. 14. Plastering and flooring works are underway on the 12th floor of stairwells A and B.