December 2024
At the construction site, reinforced concrete works have been completed in Staircase A, and the slab above the 16th floor has been finished. Currently, window installation is underway on the 8th floor of Staircases A and B. On the 7th floor of the same staircases, finishing works are in progress, including plastering, flooring, and installation tasks. In the garage, fire doors and storage units are being installed, and resin flooring is being laid. The western façade of Staircase C has been completed, while the work on the western façade of Staircase D is nearing completion. Ceiling painting and lighting fixture installation are also underway in the corridors of Staircases C and D.
We are keeping up the pace and steadily advancing through the next stages of construction!