July 2025
We are pleased to announce that the first part of The Upper House has obtained its occupancy permit. This is a significant milestone that brings us closer to the completion of the entire development. In the coming weeks, the first residents will receive the keys to their new apartments.
In July, facade installation on Building A was completed. In Building B, the west facade has been finalized, while work on the north and south facades—on floors 17 to 17A—is nearing completion. Final works on the east facade are also underway.
On Building B, roofing layers continue to be installed. Meanwhile, on the roof of Building A, installation of mechanical ventilation and air-conditioning systems is in progress.
Plastering works on floors 15 and 16 have been completed in both Buildings A and B. In Building A, wallpapering of the corridors has been completed on floors 5 through 9. Door joinery installation to residential units is ongoing in stairwells A and B.
In the main lobby, stone flooring has been fully installed. Interior finishing works are progressing in the coworking space, lobby, residence lounge, and kids’ room.
In the pool area, ceiling and wall construction is ongoing, along with the installation of sanitary systems. At the same time, landscaping works are being carried out along Miernicza Street.