07 Construction log

September 2025

September works at The Upper House have brought further visible progress.
On Building B, installation of mechanical ventilation and air-conditioning systems is ongoing. Flooring has been completed, while plastering on the 17A floor is nearing completion. In the common areas of Buildings A and B, wallpaper installation on the corridors is in progress. In the lobby, wallpapering continues along with the installation of electrical fittings, mechanical equipment, and door joinery.
In the pool area, ceramic tiles are being laid in the SPA zone. At the same time, sauna installation and suspended ceiling works in the pool area are underway.
In the coworking space, finishing works are being carried out in the sanitary rooms.
In the land development area (PZT), small architecture elements such as planters and concrete benches are being installed, alongside landscaping and greenery planting.