September 2024
Construction on Staircases A and B has reached the 11th floor, with window installations currently progressing on the 5th and 6th floors. On Staircase C, both masonry and plastering work have been completed. Flooring is being installed from the 8th floor upward on Staircase C, while plastering and flooring work has begun on the 3rd floor of Staircase A. Progress is moving smoothly, with noticeable advancements at every stage of the project.