May 2025
Wooden joinery has been fully installed throughout the entire building. Installation of the aluminum façade and glazing is in progress on the 16th and 16A floors of stairwell B. Roofing works continue on stairwell A, where the top layer of roof insulation is currently being laid. In the patio area, gypsum board walls are being installed. In the swimming pool area, waterproofing of the pool basin has been completed, and finishing layer installation is now starting. As part of the land development (PZT), shrubs and greenery are being planted on the piazza. Elevator installation in stairwell A has been completed. Glass balustrades are 90% finished. At the same time, installation of the terrace decking is underway on the stairwell B building. Façade works on the buildings of stairwells A and B are 70% complete. 13. Plastering and flooring on the 13th and 14th floors of stairwell A are nearing completion.