October 2024
Construction work is progressing rapidly! On staircase A, we’ve already reached the 13th floor, while staircase B has reached the 12th floor – the building is rising quickly before our eyes. The installation of windows on the 7th floor of staircases A and B has been completed, marking a significant step forward. Staircases C and D have reached the enclosed shell stage, with all plastering and flooring done – a major milestone! The roof on these staircases is nearly finished, and the facade has reached an impressive 70%. Meanwhile, staircases A and B are seeing intense work on plastering and flooring on the 4th and 5th floors, as we finalize the finishing touches in the common areas of staircases C and D.